Progress Interchem (Thailand)’s waste-to-energy plant of 4.8 MW starts commercial operation

Construction News

Progress Interchem (Thailand)’s waste-to-energy plant of 4.8 MW starts commercial operation

A waste-to-energy plant with an installed capacity of 4.8 MW has started commercial operation in Thailand on December 27, Thai company B.Grimm Power PCL (SET:BGRIM) said in a bourse filing on Monday.

The project has been developed by Progress Interchem (Thailand) Co Ltd in which B.Grimm holds a 48% stake. The project company has signed a 20-year power purchase agreement (PPA) with Bangkok-based Provincial Electricity Authority (PEA) for the output of the plant.

The facility uses pyrolysis technology to generate energy from industrial waste.

Source: https://renewablesnow.com/news/to-the-point-thai-waste-to-energy-plant-of-48-mw-starts-ops-681985/