A river closure ceremony of the lower Russei Chrum river was held on Tuesday in Mondol Sima district of Koh Kong province for the construction of
The ceremony was attended by Cambodian Prime Minister Hun Sen, Chinese ambassador to
Speaking at the ceremony, Prime Minister Hun Sen highly valued the friendly relations between
“The hydropower dam is just one of the numerous achievements under the cooperation between
He cited the five hydropower dams being constructed by Chinese companies such as Kamchay Hydropower with the capacity of 193 megawatts, Kirirom 3 with the capacity of 18 megawatt, Tatay river hydropower dam with the capacity of 246 megawatt, Atay hydropower dam of 120 megawatt and the Russei Chrum Krom with the capacity of 338 megawatt.
State-owned China Huadian Corp., one of
Yun Gongmin, general manager of China Huadian Corporation ( Huadian Group), said that the hydropower dam is the biggest project in
“I believe that with the strong support from Prime Minister Hun Sen and relevant ministries, the construction of the hydropower dam will be built successfully and it will become another friendship and economic cooperation milestone between
The project is a contract of a 35-year build-operate- transfer (BOT) with the local government. The total power generation is about 1.02 billion kwh per year.
The construction of the power plant began in April, 2010. So far 10 percent of the project has completed and it is scheduled to be entirely completed by 2014, said Minister Suy Sem at the ceremony.
Copyright 2010 Xinhua News Agency
Xinhua General News Service
Source: http://www.hydroworld.com/index/display/news_display.1330587172.html